PHOTOGRAPHS OF THE PROJECT



This may take a few moments to load...

EXTERIOR PHOTOS

Click here to return to the previous page

ElliottFront060699a.jpg (22987 bytes)   

LEFT: Front (south) elevation. The bay window to the left will be removed and replaced with a regular 6-over-9 window. (2/99) CENTER: Front facade after the removal of the Italianate Bay (6/99) RIGHT: The beginnings of change. (12/99)

shutterhook.jpg (49992 bytes)

ABOVE: The house's only extant original shutter hook.

Elliott012003d.jpg (16527 bytes) Elliott032703d.jpg (31072 bytes) Elliott042803a.jpg (29663 bytes) Elliott062303.jpg (47103 bytes) Elliott090803a.jpg (41636 bytes)

 LEFT: Notice new window opening on front and addition in rear (01/03) 2ND FROM LEFT: Windows have been restored and re-installed on second floor (03/03)  MIDDLE: Windows have been installed on first floor...new front porch under construction 2ND FROM RIGHT: House after removal of paint (06/20/03) RIGHT: September 2003

Elliott060803a.jpg (34736 bytes) Elliott060803b.jpg (33314 bytes) Elliott060803c.jpg (35027 bytes) Elliott062003a.jpg (42844 bytes)

ABOVE: Details of Front Porch (06/03)

FrontNov02.jpg (48313 bytes) FrontNov02b.jpg (39458 bytes) Elliott012003e.jpg (27789 bytes)  Elliott012003f.jpg (30532 bytes)

ABOVE: Process of filling hole left by the removal of the circa 1870s bay window. A six-over-nine window will be placed in the new opening, as this is what would have been there. This work is being done by Brad Parr of Lynchburg. (11/02) (01/03)

Elliott040303a.jpg (29375 bytes)  Elliott040303b.jpg (26507 bytes)  Elliott040303c.jpg (22189 bytes)

ABOVE: First phase of construction of window frame in new opening. Note...the top (horizontal) member of the brick moulding is an inch taller than its mate on the right side of the house because the new jack arch is only 2 courses tall, not 2 1/4 courses like the other first floor jack arches.

ElliottRear1.jpg (49752 bytes)

LEFT: Rear (north) elevation. The space to the left will be rebuilt and doubled in size to accommodate a kitchen on the first floor and a bathroom on the second floor. (2/99) CENTER & RIGHT: Rear elevation after the demolition of the addition, which will be replaced. Marks on wall to left of doors are not ghosts of windows, but rather layers of paint. (11/99)

ElliottSide060699a.jpg (23381 bytes) Elliott060803d.jpg (34959 bytes)

LEFT: Side (west) elevation. The entire rear addition will be rebuilt and enlarged. (2/99) CENTER:  Side (east) elevation. (2/99) RIGHT: Side (east) elevation after removal of addition. The chimney can be seen on the right hand side of the photo. FAR RIGHT: Evidence of door leading from main room on first floor to wing (demolished circa 1910). Door was bricked in in early to mid 19th Century.

ElliottRear060699b.jpg (22381 bytes)ElliottRear060699a.jpg (27558 bytes)ElliottRear060699c.jpg (22233 bytes)ElliottRear060699d.jpg (24693 bytes)

ABOVE: Rear of house after addition was removed. The piles of trash that can be seen reflect a small amount of the plaster and lathe that had to be removed from the house. Note to prospective restorers: We had a number of reasons why so much plaster had to be removed. In your case, try everything you can to avoid it. It removes some of the historic fabric from the house, is very messy, and is very hard work. (06/99)

ABOVE: Rear stone patio after removal of addition. Note excavation for enlarged kitchen and bathroom to right. (11/99)




 

 

ABOVE LEFT: Detail of kitchen area after existing addition and concrete slab have been removed. Yellow lines signify approximate location of concrete slab-- note that the concrete was harder than the brick wall, causing failure of the brick because of freezing, thawing, and moisture retention. (11/99)
ABOVE RIGHT: Repaired corner of house (shown in left photo). Note that excess mortar has not been cleaned off of the face of the bricks at this point. (11/00)


 

ABOVE LEFT: To help prevent the problem in the previous photo from occurring again, there is an expansion joint between the restored brick house wall and the new concrete slab. There is also a 6 mil. moisture barrier below the slab, and the new addition will be insulated and heated, avoiding the freezing and thawing of the slab that occurred previously. Note the rough texture of the slab...ceramic tile will be laid on top of the concrete, so a perfectly smooth finish is not required. (11/00) ABOVE RIGHT: Foundation and floor slab of new kitchen/bathroom addition. The 12'x16' Kitchen will be on the first floor, with a Bathroom and Mudroom (accessed from the second floor back porch) on the second floor. (11/00)

ElliottHouse12-16-00a.JPG (45480 bytes)

ABOVE: Cinder blocks stacked in preparation for laying the kitchen walls (12/00)

ElliottHouseAddition011301c.JPG (59701 bytes) ElliottHouseAddition011301d.JPG (58360 bytes)

ABOVE LEFT & RIGHT: The framing of the first floor of the addition (kitchen) is complete. (01/01)

ABOVE LEFT & RIGHT: "Parging", a mixture of hydraulic (waterproof) portland cement and fiberglass was applied to the exterior cinder block walls. A tar-like coating was slathered on after that.

ABOVE: Interior of house, opposite damage to exterior wall seen in previous photo. Note the bricks that have been pushed inside by the concrete slab. (12/99)

ElliottHouseAddition101201a.JPG (49067 bytes)ElliottHouseAddition101201b.JPG (39173 bytes)

ABOVE: Completion of framing for second floor of addition (first floor will contain a kitchen. Second floor will contain a laundry room and bathroom). (10/01)

March2002a.jpg (49701 bytes) March2002b.jpg (49813 bytes) March2002c.jpg (47269 bytes) March2002d.jpg (48561 bytes)

ABOVE: Continuation of construction of rear addition. The siding is Hardiplank, a product made of cement and wood fiber. The gable roof of the addition has not yet been built. The far left hand photo shows a second floor door, which leads into a mud room. This door will open onto a porch that will run along the back of the main house, much as the late 19th century porch did.

RockWalla.jpg (37867 bytes)

ABOVE: Stone retaining wall behind rear addition, allowing the yard behind the addition to maintain level. The completion of the siding on the addition can be discerned from this photo as well. (6/02)

Elliott012003a.jpg (34385 bytes)  Elliott012003b.jpg (18554 bytes)  Elliott032703a.jpg (28571 bytes)

ABOVE LEFT & CENTER: Rear addition almost complete (01/03)

ABOVE RIGHT: Rear addition complete (03/03)

      Elliott102002a.jpg (32416 bytes) Elliott102002b.jpg (22894 bytes) Elliott122002a.jpg (31922 bytes) Elliott012003c.jpg (32252 bytes) Elliott032703b.jpg (29902 bytes) Elliott032703c.jpg (26929 bytes)

ABOVE: Construction of new back porch (10/02-01/03)

TWO PHOTOS TO RIGHT: (03/03)

Elliott060803e.jpg (38433 bytes) Elliott062303b.jpg (41942 bytes) Elliott090803b.jpg (48119 bytes) Shutters101103a.jpg (46996 bytes) Shutters101103b.jpg (48066 bytes)

ABOVE LEFT & 2ND FROM LEFT: June 2003 MIDDLE: Installation of electrical service entry (09/03) RIGHT: Installation of paneled shutters on back porch (10/03)

Elliott031404a.jpg (40500 bytes) Elliott031404b.jpg (58522 bytes)

ABOVE: Copper chimney cap, step flashing, ridge cap installation (also loose slate repairs) (3/04)

DSCN3378.JPG (337529 bytes) DSCN3379.JPG (324132 bytes) DSCN3380.JPG (378527 bytes) DSCN3381.JPG (395277 bytes)

ABOVE: Slate and Owens-Corning Berkshire Shingles installed on rear of house (8/05)

Click here to return to the previous page